Contract: EPCC
Technical Data:
250, 000 t/y Polystyrene

Contract: EPCC
Technical Data:
250, 000 t/y Polystyrene




Contract: EPC
Technical Data:
2,700m two arms of breakwater
Up to 35m water depth,
Fifteen posts of various types of
wharf including LNG and LPG

Contract: EPC
Technical Data:
The project includes the dredging of basin, reclamation of new land for construction sulfur berth, construction of two LPG berths and breakwater with 4,657m long.

Contract: EPC
Technical Data:
940 m of breakwaters,
Construction of 2,600 m dike
for land reclamation.
Two posts of LNG and LPG
jetties

Contract: EPCC Technical Data: 2 × 130 Ton/day Liquid Sulphur from acid gas TGTU, 95% to 99.7% efficiency

Contract: EPCC / EP / MC / SSC
Technical Data:
58, 57, 54, 52, 30, 30
MMSCMD for compressor
stations,
Different spec for turbo
compressors


Contract: EP + Pre-commissioning + Commissioning
Technical Data:
180 MMSCFD of Feed Gas,
4,400 BBIS/D of Feed Condensate


Contract: EP
Technical Data:
50 MMSCFD Natural Gas
6,900 BPD Propane
3,750 BPD Butane
3,180 BPD Condensate

Contract: EP
Technical Data:
4 * 1,000 MMSCFD Natural Gas
4 * 40,000 BBLS/D Condensate

Contract: EPC
Technical Data:
Engineering, Procurement and Construction of Pars Service Port...

Contract: EPC Technical Data: Dredging and deepening of big Tianjin Port and binghai port around 10,000,000 m3 and discharge 8km.

Contract: EPC
Technical Data:
Procurement and Construction of Kish Port Complex development including:
Dredging & Reclamation about 700,000 m3.

Contract: EPC
Technical Data:
Engineering, Procurement and Construction of 2nd phase of SRB Port Complex Development.
Dredging & Land Reclamation with Total Volume about 8,000,000 m3 in one Phase...

Contract: EPC
Technical Data:
Capacity : 2000 m3/hr
Design, Procurement and Construction
of Water Intake, Treatment Plant,
Pump Stations and 17 Km Ductile
Iron Pipeline up to 700 mm Dia

Contract: EPC
Technical Data:
Water treatment plant: 600 lit/sec
Pipeline(GRE): 350 km

Contract: EPC
Technical Data:
Clarified Water: 7000 m3/hr,
DM Water: 980 m3/hr,
CPP: 555 m3/hr,
Service Water: 400 m3/hr,
Potable Water: 250 m 3/hr,
RO Water: 3900 m3/hr,
Firefighting Water: 7000 m3/hr,
Cooling Water: 2400 m3/hr,

Contract: EPC
Technical Data:
RO Water: 1560 m3/hr
DM Water: 490 m3/hr
CPP: 275 m3/hr

Contract: EPC
Technical Data:
RO Water: 5460 m3/hr
Potable Water: 125 m3/hr
Cooling Water: 9000 m3/hr
DM Water: 1470 m3/hr
CPP: 400 m3/hr

Contract: EPC
Technical Data:
Treated Water: 200 m3/hr
Intake from River
17 Km pipeline(HDPE)
Conventional Water Treatment
Reservoir 2500 m3(C.S)

Contract: EPC
Technical Data:
Low Salinity Effluent: 421 m3/hr
High Salinity Effluent: 70 m3/hr
Sanitary Effluent: 69 m3/hr


Contract: EPC
Technical Data:
Treated Water: 180 m3/hr
Cold lime-Soda softening process

Contract: EPC
Technical Data:
Treated Water: 2000 m3/day
Conventional activated sludge (extended aeration)
Tertiary treatment
Processed effluent for drip irrigation

Contract: EP
Technical Data:
Condensate De-oiling 750 m3/hr
Hot Condensate Polishing 750 m3/hr
Cold Condensate Polishing 300 m3/hr
Demin 400 m3/hr

Contract: EPC
Technical Data:
Clarified Water: 844 m3/hr
CPP: 410 m3/hr
DM Water: 293 m3/hr
Potable water: 12 m3/hr